Power shutdown in Kashmir

SRINAGAR: According to the Power Controller Kashmir, in order to carry out various works, there will be a power shutdown in various areas of Ganderbal and Bandipora.

According to details, in order to carry the laying and stringing of the conductor of 132 kV BBTL at Ajas, Bandipora, 33KV HCC feeder will be shutdown. In this regard the power supply to the areas fed from this feeder shall remain affected on 17, 19 and 20 March 2019 from 10.00 AM to 5.00 PM.

In Ganderbal, the department intends to carry out branch cutting, repairs and stabilization of the 33KV Habbak Ganderbal line.

In this regard receiving stations of Alasteng, Nagbal, Power House, Ganda Singh, Tullabagh and Mangam will remain shutdown and the power supply to the area fed from the said receiving stations shall remain affected on 16 and 23 March 2019 from 10.00 AM to 5.00 PM.